Rooftop solar installation at Coco Grove Siquijor
All projectsHOSPITALITY · PROJECT

Solar power for
Coco Grove Siquijor.

A resort hybrid solar installation in San Juan, Siquijor.

San Juan, Siquijor, Philippines
PROJECT OVERVIEW

Reliable energy for a destination resort.

Coco Grove welcomes guests across resort rooms, dining spaces and shared facilities. The project pairs rooftop solar with battery storage to use more locally generated power during the day and support selected loads when the grid is unavailable.

Solar array60 × 550 W panels
System capacity33 kWp DC · 30 kW AC
Battery storage40.96 kWh usable
System typeGrid-connected hybrid
Project locationSan Juan, Siquijor
Installation period18 working days
BUSINESS CONTEXT & ENERGY USE

Designed around the site.

Coco Grove welcomes guests across resort rooms, dining spaces and shared facilities. The project pairs rooftop solar with battery storage to use more locally generated power during the day and support selected loads when the grid is unavailable.

The array is sized to cover a large share of daytime demand, while storage shifts some solar energy into evening operations. The grid remains available as a backup source.

INSTALLATION

From site work to handover.

01

Site assessment

Roof structure, shading and resort load profiles were reviewed before final equipment placement.

02

Mounting and array

The crew installed roof mounts, rails and panel strings across two low-slope service buildings.

03

Electrical integration

Inverters, battery cabinets and protection devices were wired into the designated resort distribution board.

04

Testing and handover

The system was inspected, commissioned and handed over with monitoring access and operator orientation.

ESTIMATED IMPACT

Indicative project outcomes.

Estimated output and savings are based on the installed system size and typical sunny-site conditions. Actual performance varies with weather, shading, load profile and system operation.

estimated monthly generation3,900 kWh
estimated CO₂ avoided monthly~2.7 t
daytime energy offset70%
A PRACTICAL NEXT STEP

Have a site with similar energy needs?

Talk with the Repeat Solar team about a system designed around your property.

Coco Grove Siquijor Solar Case Study | Repeat Solar